Stay up to date with the progress of Silverpoint.

Construction Updates Kathlien Perez Construction Updates Kathlien Perez

Detailing and Final Cleaning in Progress

Level 1 & 2: Both levels have reached practical completion. Detailing, final cleaning and installation of fly screens are now in progress. Level 1 common hallway carpets have been fitted with Level 2 to follow this week.
Level 3: Carpet has been fitted in all penthouses. Penthouse garage roller doors have been installed. Minor touch-ups, detailing, final cleaning and installation of fly screens are now in progress. Level 3 common hallway carpets to be installed after all penthouse interiors reach practical completion.
Common Areas: BBQ area, storage cages, main entry paving and side sheds are now complete. Cleaning of the ground floor parking and building external is now is now in progress. New fencing to the rear of the building to be installed very soon.

Read More
Kathlien Perez Kathlien Perez

Final Stage

Levels 1 - 2: All internal work are now completed. Protective covering on the flooring are installed until final clean.

Level 3: Carpet installation in progress.

External: Landscaping work is currently being undertaken which is typically indicates the final stage of the build. Pavers are being laid and the gardens are going in today.

We are pleased to share the fire inspection is also happening today. This is to obtain a Fire Safety Certificate which is required when new building work is complete. This certificate confirms that a properly qualified person has installed and checked the measures listed in the fire safety schedule. This helps verify that the measures can perform to the minimum standard. However, we may have to wait for a NSW Fire Brigade inspection that we will know more about later this week.

A statement from the Coho Property construction team will be issued by Friday, 1 November 2024 to better guide you with a timeline to plan and prepare for settlement.

We thank you for your patience and understanding during this time while the construction team prioritise construction completion and compliance checks in preparation to obtaining the Occupancy Certification and Title Registration.

Please do not hesitate to contact us on 1800 966 994 if you require any further information.

Read More
Announcements Kathlien Perez Announcements Kathlien Perez

Display Suite Visits Resuming in November

Thank you for your interest in visiting the Silverpoint onsite display suite. Construction completion is our highest priority at present therefore, all display suite visits are on hold until November 2024.

Please contact Kat Perez on 0475 449 078 for more information on the final 2 Silverpoint apartments or to find out the next available appointment. We thank you for your understanding.

Read More
Announcements Kathlien Perez Announcements Kathlien Perez

Your Final Chance at Silverpoint

Final 2 apartments available for sale:

  • 103 - $830k: 2 bedrooms, 2 bathrooms, 1 car space

  • 104 - $850k: 2 bedrooms + study, 2 bathrooms, 1 car space

You are invited to experience our exclusive onsite display suite situated on the ground floor of 20 Government Road, Nelson Bay, available by appointment only. To arrange your visit, please contact us on 1800 966 994 or info@cohoproperty.com.au.

Read More
Construction Updates Kathlien Perez Construction Updates Kathlien Perez

September 2024

Silverpoint scaffolding has come down revealing the facade of the building.

  • Level 1 - Carpets, robes and light fixtures are now installed. Balcony pavers are now in progress.

  • Level 2 - Light fixtures are now installed. Balcony pavers, robes and carpet are now in progress.

  • Level 3 - Tiling, flooring and joinery installation now in progress.

Balustrades have been installed for all balconies.

Read More
Announcements Kathlien Perez Announcements Kathlien Perez

August 2024

Scaffolding coming down now revealing the facade as the countdown to completion begins

  • Level 1 – Kitchen appliances, bathrooms, laundry, wardrobes and flooring now installed. Balcony paving now in progress.

  • Level 2 – Bathrooms and wardrobes installation now complete. Joinery installation in laundry and kitchen now in progress. Flooring and balcony paving  commencing soon.

  • Level 3 – Plasterboard and painting now complete. Tiling now in progress. Kitchen, wardrobe and laundry installation commencing soon.

Our current projected completion remains to be for Occupational Certificate in mid-October. Please note it is typical for title registration to take 2-3 weeks following Occupational Certificate.

Read More
Construction Updates Kathlien Perez Construction Updates Kathlien Perez

July 2024

Since commencing presales in March 2024, our Silverpoint Nelson Bay project has garnered a remarkable response. We wish to express our appreciation for the unwavering dedication of our building partner, Drew Construction Group, whose diligent efforts onsite are ensuring a high quality project is delivered during challenging industry conditions.

Our current projected completion is for Occupational Certificate in mid-late October. We have experienced delays due to inclement rainy weather preventing a clear run at rendering of external areas, and a material supply constraint delaying completion of the Level 3 external walls. Now the latter is resolved we will see the scaffolding come down in stages from mid-August.

  • Ground Floor – Main building entry door and lift now installed

  • Level 1 – Tiling, flooring and joinery installation now complete

  • Level 2 – Tiling, flooring and joinery installation now in progress

  • Level 3 – Plasterboard and painting now in progress

Read More
Announcements Kathlien Perez Announcements Kathlien Perez

Final 3 Residences Remaining

With over 80% of Silverpoint now sold, only 3 residences remain available for sale. This represents your final opportunity to secure a residence at Silverpoint. You are invited to experience our exclusive onsite display suite situated on the ground floor of 20 Government Road, Nelson Bay, available by appointment only.

To arrange your visit, please contact us on 1800 966 994 or info@cohoproperty.com.au.

Read More
Construction Updates Kathlien Perez Construction Updates Kathlien Perez

June 2024

Level 1 - Tiling and joinery installation now in progress.

Level 2 - All plasterboard is complete and painting has commenced, Tiling is now also in progress.

Level 3 - Roof, services and rough-ins are now completed.

Read More