Detailing and Final Cleaning in Progress
Level 1 & 2: Both levels have reached practical completion. Detailing, final cleaning and installation of fly screens are now in progress. Level 1 common hallway carpets have been fitted with Level 2 to follow this week.
Level 3: Carpet has been fitted in all penthouses. Penthouse garage roller doors have been installed. Minor touch-ups, detailing, final cleaning and installation of fly screens are now in progress. Level 3 common hallway carpets to be installed after all penthouse interiors reach practical completion.
Common Areas: BBQ area, storage cages, main entry paving and side sheds are now complete. Cleaning of the ground floor parking and building external is now is now in progress. New fencing to the rear of the building to be installed very soon.