The Silverpoint onsite display suite opening has been such a huge success. We have been overwhelmed by feedback from our visitors on the quality of the build, variety and spaciousness of the floor plans particularly from our downsizing clients and the interior finishes selection from the display suite.
Roof going on from 6 May 2024 despite the frequent heavy rain in Nelson Bay lately.
Level 1 – Painting and tiling complete, joinery expected to be completed by end-May.
Level 2 – Painting and tiling to be completed by end-May.
Level 3 – Walls are up and now waiting for roof to finish off, services rough-in and sheeting.
Our current schedule for Silverpoint has Occupational Completion in August – more accurate timing to be provided in the coming months.